Stay informed with the Sizewell C Works Tracker, your tool for tracking construction progress. Access up-to-date information on work locations and timings. Use filters for dates, locations, and types of work. Contact us for more information or feedback as we work towards providing low-carbon electricity to six million homes.
AIL movements in relation to the Sizewell C Project On Monday 1 September, there are four wide load movements currently planned: At 09:00, two dumper trucks are being collected from the Temporary Construction Area. At 11:00, plant is being delivered […]
AIL movements in relation to the Sizewell C Project On Monday 1 September, there are four wide load movements currently planned: At 09:00, two dumper trucks are being collected from the Temporary Construction Area. At 11:00, plant is being delivered […]
Following a recent review, Sizewell C have submitted a planning application to East Suffolk Council to slightly raise the elevation of the southern section of the temporary sea defence wall, from 7.3 metres to 10 metres above sea level. The […]
Welcome to the July round up of activity at Sizewell C. Sizewell C has secured its Final Investment Decision (FID), giving the green light to the nuclear plant. We have announced the new shareholders of the project, with the government […]
As part of the enabling works for the Sizewell C nuclear power station, construction of the temporary sea defence (TSD) which has been ongoing over the last few months and will include this and subsequent weekends. This essential infrastructure is being installed […]
Average Speed Cameras in Operation Sizewell C can confirm the installation of Average Speed Cameras along the B1122 between the level crossing and Eastbridge Road, and on the B1125 at Westleton, as requested by their respective parish councils, has now […]
Welcome to the June edition of the Sizewell C update on project progress. Key updates about works on each site can be found below. It is worth noting that enforcement of the 30mph speed limit by average speed cameras average […]
From The Environment Agency: The Environment Agency shares permit applications and consultations online here: Nuclear consultations – Environment Agency – Citizen Space New abstraction licence consultation: NPS/WR/040323 The Environment Agency has received an application for a licence to abstract water […]
Sizewell C has now installed average speed cameras along the B1122 and B1125 to further enhance road safety in the new 30mph speed limit. Further speed restrictions along the A12 are being implemented, including south of Yoxford. This is to […]
Welcome to the May edition of the Sizewell C project update. Pre construction works are progressing well throughout all our sites. The roads, roundabouts and park rides will start construction this summer. The main site and temporary construction area are […]
Activity: Site construction
Activity: Traffic management
Start date: 31st October 2023
End date: 31st December 2026
Activity: Site construction
Activity: Ecological work
Start date: 26th June 2024
End date: 30th September 2025
Activity: Site construction
Start date: 30th September 2024
End date: 30th April 2026
Activity: Site construction
Activity: Road closures
Start date: 16th December 2024
End date: 1st January 2027
Activity: Traffic management
Start date: 20th January 2025
End date: 31st January 2026
Activity: Road closures
Start date: 20th January 2025
End date: 13th January 2027
Activity: Site construction
Start date: 17th March 2025
End date: 31st December 2025
Activity: Site construction
Start date: 2nd May 2025
End date: 1st January 2026
Activity: Site construction
Start date: 5th May 2025
End date: 31st December 2025
Activity: Marine
Start date: 19th May 2025
End date: 31st December 2025
Activity: Site construction
Start date: 19th May 2025
End date: 31st December 2025
Activity: Traffic management
Start date: 19th May 2025
End date: 31st December 2026
Activity: Site construction
Start date: 26th May 2025
End date: 2nd March 2026
Activity: Site construction
Start date: 27th May 2025
End date: 31st December 2025
Activity: Footpath diversions
Start date: 1st June 2025
End date: 31st December 2025
Activity: Footpath diversions
Start date: 1st June 2025
End date: 31st December 2025
Activity: Footpath diversions
Start date: 1st June 2025
End date: 31st December 2025
Activity: Footpath diversions
Start date: 1st June 2025
End date: 31st December 2025
Activity: Site construction
Start date: 1st July 2025
End date: 6th August 2027
Activity: Traffic management
Start date: 7th July 2025
End date: 31st December 2026
Activity: Traffic management
Start date: 7th July 2025
End date: 31st December 2026
Activity: Traffic management
Start date: 7th July 2025
End date: 31st December 2026
Activity: Footpath diversions
Start date: 4th August 2025
End date: 4th August 2027
Activity: Road closures
Start date: 4th August 2025
End date: 20th December 2025
Activity: Road closures
Start date: 31st August 2025
End date: 7th September 2025
Activity: Road closures
Start date: 8th September 2025
End date: 12th October 2025
Activity: Road closures
Start date: 22nd September 2025
End date: 8th October 2025
Activity: Road closures
Start date: 22nd September 2025
End date: 30th September 2025
Activity: Road closures
Start date: 6th October 2025
End date: 10th October 2025
Be the first to know about key announcements and new information as it becomes available. Whether you're a local resident, stakeholder, or simply interested in the project, our updates will keep you in the loop and provide valuable insights directly to your inbox. Don't miss out. Register today and stay connected!
"*" indicates required fields