Stay informed with the Sizewell C Works Tracker, your tool for tracking construction progress. Access up-to-date information on work locations and timings. Use filters for dates, locations, and types of work. Contact us for more information or feedback as we work towards providing low-carbon electricity to six million homes.
AIL movements in relation to the Sizewell C Project On Monday 4 August, there are two wide load movement currently planned: At 10:00, an excavator will be leaving the Temporary Construction Area. At 11:00, plan machinery will be delivered the […]
AIL movements in relation to the Sizewell C Project On Wednesday30 July, there are two wide load movement currently planned: At 09:00, a plant equipment will be leaving the Temporary Construction Area. At 13:00, a dumper truck will be […]
As part of the enabling works for the Sizewell C nuclear power station, construction of the temporary sea defence (TSD) which has been ongoing over the last few months and will include this and subsequent weekends. This essential infrastructure is being installed […]
Average Speed Cameras in Operation Sizewell C can confirm the installation of Average Speed Cameras along the B1122 between the level crossing and Eastbridge Road, and on the B1125 at Westleton, as requested by their respective parish councils, has now […]
Welcome to the June edition of the Sizewell C update on project progress. Key updates about works on each site can be found below. It is worth noting that enforcement of the 30mph speed limit by average speed cameras average […]
The current works along the A12 slip road and B1116 are being carried out by Cadent Gas who have put in place an emergency closure and diversion route along the A12 Hacheston Northbound Slip Road only. These works are not […]
From The Environment Agency: The Environment Agency shares permit applications and consultations online here: Nuclear consultations – Environment Agency – Citizen Space New abstraction licence consultation: NPS/WR/040323 The Environment Agency has received an application for a licence to abstract water […]
Sizewell C has now installed average speed cameras along the B1122 and B1125 to further enhance road safety in the new 30mph speed limit. Further speed restrictions along the A12 are being implemented, including south of Yoxford. This is to […]
Welcome to the May edition of the Sizewell C project update. Pre construction works are progressing well throughout all our sites. The roads, roundabouts and park rides will start construction this summer. The main site and temporary construction area are […]
From The Environment Agency: The Environment Agency shares permit applications and consultations online here: Nuclear consultations – Environment Agency – Citizen Space Permit application: EPR/HB3542KC/A001 for Construction Water Discharge Activity for the ‘Main Development Site’ The Environment Agency has received […]
Activity: Site construction
Activity: Traffic management
Start date: 31st October 2023
End date: 31st December 2026
Activity: Site construction
Activity: Ecological work
Start date: 26th June 2024
End date: 30th September 2025
Activity: Archaeology
Start date: 16th August 2024
End date: 1st September 2025
Activity: Site construction
Start date: 30th September 2024
End date: 30th April 2026
Activity: Site construction
Activity: Road closures
Start date: 16th December 2024
End date: 1st January 2027
Activity: Traffic management
Start date: 20th January 2025
End date: 31st January 2026
Activity: Road closures
Start date: 20th January 2025
End date: 13th January 2027
Activity: Site construction
Start date: 17th March 2025
End date: 31st December 2025
Activity: Site construction
Start date: 5th May 2025
End date: 31st December 2025
Activity: Marine
Start date: 19th May 2025
End date: 31st December 2025
Activity: Site construction
Start date: 19th May 2025
End date: 31st December 2025
Activity: Traffic management
Start date: 19th May 2025
End date: 31st December 2026
Activity: Site construction
Start date: 26th May 2025
End date: 1st September 2025
Activity: Site construction
Start date: 27th May 2025
End date: 31st December 2025
Activity: Footpath diversions
Start date: 1st June 2025
End date: 31st December 2025
Activity: Footpath diversions
Start date: 1st June 2025
End date: 31st December 2025
Activity: Footpath diversions
Start date: 1st June 2025
End date: 31st December 2025
Activity: Footpath diversions
Start date: 1st June 2025
End date: 31st December 2025
Activity: Site construction
Start date: 1st July 2025
End date: 6th August 2027
Activity: Traffic management
Start date: 7th July 2025
End date: 31st December 2026
Activity: Traffic management
Start date: 7th July 2025
End date: 31st December 2026
Activity: Railway Works
Start date: 22nd July 2025
End date: 8th August 2025
Activity: Traffic management
Start date: 25th July 2025
End date: 15th August 2025
Activity: Site construction
Start date: 31st July 2025
End date: 1st September 2025
Activity: Railway Works
Start date: 31st July 2025
End date: 8th August 2025
Activity: Wide load
Start date: 1st August 2025
End date: 8th August 2025
Activity: Footpath diversions
Start date: 4th August 2025
End date: 4th August 2027
Activity: Site construction
Start date: 11th August 2025
End date: 25th August 2025
Be the first to know about key announcements and new information as it becomes available. Whether you're a local resident, stakeholder, or simply interested in the project, our updates will keep you in the loop and provide valuable insights directly to your inbox. Don't miss out. Register today and stay connected!
"*" indicates required fields