Stay informed with the Sizewell C Works Tracker, your tool for tracking construction progress. Access up-to-date information on work locations and timings. Use filters for dates, locations, and types of work. Contact us for more information or feedback as we work towards providing low-carbon electricity to six million homes.
See below for Sizewell C current and up and coming road closures and traffic management. Road Closures Willow Marsh Lane, Darsham is closed until June 2026 to enable the construction of the Northern Park & Ride roundabout and site. […]
AIL movements in relation to the Sizewell C Project On Monday 20 October there are four wide load movements planned. At 11:00, two deliveries of sheet piles will be made to the Temporary Construction Area. At 15:00, two deliveries of […]
See below for Sizewell C current and up and coming road closures and traffic management. Road Closures Willow Marsh Lane, Darsham is closed until June 2026 to enable the construction of the Northern Park & Ride roundabout and site. Diversion […]
AIL movements in relation to the Sizewell C Project Updated 14 October On Monday 13 October there are nine wide load movements planned. At 09:00, a crane will be delivered to the Temporary Construction Area. At 10:00, three cranes will […]
AIL movements in relation to the Sizewell C Project On Monday 6 October, there are eight wide load movements currently planned: At 10:00am, a crane will be delivered to the Main Construction Area. At 11:00, two storage tanks will be […]
From Monday 6th October, you will notice changes to the junction at Lovers Lane and Abbey Road (B1122). We will be opening the realigned Lovers Lane–Abbey Road junction. However, to facilitate the installation of a new level crossing on Abbey […]
See below for Sizewell C current and up and coming road closures and traffic management. Road Closures Willow Marsh Lane, Darsham is closed until June 2026 to enable the construction of the Northern Park & Ride roundabout and site. […]
Welcome to the latest round up of construction activity at Sizewell C. We are pleased to announce our SMS alert service is now live, the community can now sign up to receive works tracker updates via SMS as well as […]
AIL movements in relation to the Sizewell C Project Updated 1 October. On Tuesday 30 September, there are ten wide load movement currently planned: At 09:00am, two modular buildings will be delivered to the Main Construction Area. At 11:00, a […]
Please see below the current traffic management and road closures currently in place. Road Closures Willow Marsh Lane, Darsham is closed until June 2026 to enable the construction of the Northern Park & Ride roundabout and site. Diversion in place […]
Activity: Site construction
Activity: Site construction
Activity: Ecological work
Start date: 26th June 2024
End date: 30th September 2026
Activity: Site construction
Start date: 16th August 2024
End date: 31st December 2025
Activity: Site construction
Start date: 30th September 2024
End date: 30th April 2026
Activity: Site construction
Activity: Site construction
Start date: 7th October 2024
End date: 31st January 2026
Activity: Road closures
Start date: 16th December 2024
End date: 1st January 2027
Activity: Traffic management
Start date: 20th January 2025
End date: 31st January 2026
Activity: Road closures
Start date: 20th January 2025
End date: 13th January 2027
Activity: Site construction
Start date: 17th March 2025
End date: 31st December 2025
Activity: Site construction
Start date: 2nd May 2025
End date: 1st January 2026
Activity: Site construction
Start date: 5th May 2025
End date: 31st December 2025
Activity: Site construction
Start date: 19th May 2025
End date: 31st December 2025
Activity: Traffic management
Start date: 19th May 2025
End date: 31st December 2026
Activity: Site construction
Start date: 26th May 2025
End date: 2nd March 2026
Activity: Site construction
Start date: 27th May 2025
End date: 31st December 2025
Activity: Footpath diversions
Start date: 1st June 2025
End date: 31st December 2025
Activity: Footpath diversions
Start date: 1st June 2025
End date: 31st December 2025
Activity: Footpath diversions
Start date: 1st June 2025
End date: 31st December 2025
Activity: Footpath diversions
Start date: 1st June 2025
End date: 31st December 2025
Activity: Site construction
Start date: 1st July 2025
End date: 6th August 2027
Activity: Traffic management
Start date: 7th July 2025
End date: 31st December 2026
Activity: Traffic management
Start date: 7th July 2025
End date: 31st December 2026
Activity: Traffic management
Start date: 7th July 2025
End date: 31st December 2026
Activity: Footpath diversions
Start date: 4th August 2025
End date: 4th August 2027
Activity: Traffic management
Start date: 4th August 2025
End date: 20th December 2025
Activity: Site construction
Start date: 5th September 2025
End date: 15th January 2026
Activity: Site construction
Start date: 5th September 2025
End date: 9th January 2026
Activity: Site construction
Start date: 15th September 2025
End date: 31st December 2025
Activity: Site construction
Start date: 15th September 2025
End date: 9th January 2026
Activity: Site construction
Start date: 2nd October 2025
End date: 14th November 2025
Activity: Site construction
Start date: 15th October 2025
End date: 1st March 2026
Activity: Wide load
Start date: 17th October 2025
End date: 24th October 2025
Activity: Road closures
Start date: 20th October 2025
End date: 20th December 2025
Activity: Road closures
Start date: 20th October 2025
End date: 20th December 2025
Be the first to know about key announcements and new information as it becomes available. Whether you're a local resident, stakeholder, or simply interested in the project, our updates will keep you in the loop and provide valuable insights directly to your inbox. Don't miss out. Register today and stay connected!
"*" indicates required fields