4th Oct 2024

< BACK News

Wide & Abnormal Load movements w/c 7 October

AIL movements in relation to the Sizewell C Project.

Updated 10 October 2024.

On Monday 7 October, there is one abnormal load movement planned:

This load will be an articulated dump truck departing the Temporary Construction Area at approximately 9am and will be police escorted. This load will follow the designated route from site – Lovers Lane, B1122 west, A12 south, towards Ipswich.

On Wednesday 9 October, there are three wide load movements planned.

The first two loads will be travelling to the Temporary Construction Area, delivering Articulated Dump Trucks. These are expected to arrive at 10:00 am.

These loads will follow the designated route to and from site – A12, B1122 East and Lovers Lane.

The third load will be travelling to the Temporary Construction Area, delivering an excavator. This is expected to arrive at 11:00 am.

This load will follow the designated route to and from site – A12, B1122 East and Lovers Lane.

On Thursday 10 October, there are three abnormal load movements planned:

The first will be travelling to the Temporary Construction Area, delivering a dozer. This will arrive at approximately 11am and will be police escorted.

The second and third deliveries of dozers will both be travelling to the Temporary Construction Area, will be police escorted, and will arrive at approximately 1pm.

These loads will follow the designated route to and from site – A12, B1122 East, Lovers Lane and Sizewell Gap Road.

On Friday 11 October, there are five wide load movements planned:

The first load will be travelling from Wild Aldhurst to the Main Development Site, relocating an articulated dump truck. This is expected to arrive at 09:00 am.

This load will follow the designated route to and from site – along Lovers Lane.

The remaining loads will be travelling to the Two Village Bypass compound at Tinkerbrook, delivering a dozer and articulated dump trucks. These are expected to arrive at 11:00 am, 12:00pm and two loads at 14:00pm

These loads will follow the designated route to and from the site compound, along the A12.