back
Farnham with Stratford St Andrew, Hacheston, Leiston, Leiston-cum-Sizewell, Marlesford, Melton, Middleton cum Fordley, Theberton and Eastbridge, Woodbridge

Main Development Site

Activity: Wide Load

Start date: 11th October 2024

End date: 19th October 2024

Week commencing 14 October 2024.

Updated 14 October 2024.

On Monday 14 October, there are two wide load movements planned.

These loads are the collection of articulated dump trucks from the Ancillary Construction Area. These loads are expected to depart at 11:00 am.  These will be police escorted.

These loads will follow the designated route to and from site – Lovers Lane, B1122 West and A12.

On Wednesday 16 October, there are five wide load movements planned.

The first two loads will be traveling to the Temporary Construction Area, delivering articulated dump trucks. These are expected to arrive at 10:00 am. These loads will be police escorted.

These loads will follow the designated route to and from site – A12, B1122 East and Lovers Lane.

The third load will be traveling to the Main Construction Area, delivering a chipper. This is expected to arrive at 11:00 am. This load will be police escorted.

These loads will follow the designated route to and from site – A12, B1122 East and Lovers Lane.

The fourth and fifth load, will be collecting bulldozers from the Temporary Construction Area. These loads are expected to depart at 12:00 pm.  These will be police escorted.

These loads will follow the designated route to and from site – Lovers Lane, B1122 West and A12.

On Friday 18 October, there is one wide load movements planned.

This load will be traveling to the Temporary Construction Area, delivering plant machinery. This is expected to arrive at 11:00 am. This load will be police escorted.

This load will follow the designated route to and from site – Lovers Lane, B1122 West and A12.