Farnham with Stratford St Andrew, Hacheston, Leiston, Leiston-cum-Sizewell, Marlesford, Melton, Middleton cum Fordley, Theberton and Eastbridge, Woodbridge

Main Development Site

Activity: Wide Load

Start date: 9th September 2024

End date: 13th September 2024

Updated 10 September  2024.

On Monday 9 September, there are six wide load movements planned.

These loads will be low loaders delivering plant to the Temporary Construction Area and Main Construction Area. They are expected to arrive at 9:00am, 11:00am, 12:00 and 13:00pm and will be escorted by police.

The loads will follow the designated route to and from site – North on the A12 from Ipswich and B1122 East.

Week commencing 9 September 2024.

On Wednesday 11 September, there are three wide load movements planned.

These loads will be traveling to the Temporary Construction Area. These will arrive at 10:00 am and 15:00 pm and will be police escorted.

This load will follow the designated route to and from site – A12, B1122 East and Lovers Lane.

On Thursday 12 September, there is one wide load movement planned.

This first load will be travelling to the Main Construction Site. This load is expected to arrive at 14:00 pm and will be police escorted.

This load will follow the designated route to and from site – A12, B1122 East, Lovers Lane and Sizewell Gap Road.

On Friday 13 September, there is one wide load movement planned.

This load will be travelling to the Temporary Construction Site. This load is expected to arrive at 10:00 am and will be police escorted.

This load will follow the designated route to and from site – A12, B1122 East and Lovers Lane.